Article 17 Settlement of Disputes

    1
  • If any dispute arises between the Contracting Parties relating to the interpretation or application of this Agreement, the Contracting Parties shall in the first place endeavour to settle their dispute by bilateral negotiations.
    2
  • If the Contracting Parties fail to reach a settlement by negotiation, the dispute may at the request of either Contracting Party be submitted for decision to a tribunal of three arbitrators, one to be named by each Contracting Party and the third to be agreed upon by the two arbitrators so chosen, provided that such third arbitrator shall not be a national of either Contracting Party. Each of the Contracting Parties shall designate an arbitrator within a period of sixty (60) days from the date of receipt by either Contracting Party from the other Contracting Party of a diplomatic note requesting arbitration of the dispute and the third arbitrator shall be agreed upon within a further period of sixty (60) days. If either of the Contracting Parties fails to designate its own arbitrator within the period of sixty (60) days or if the third arbitrator is not agreed upon within the period indicated, the President of the Council of the International Civil Aviation Organization may be requested by either Contracting Party to appoint an arbitrator or arbitrators. If the President is a national of the same country as one of the Contracting Parties, the most senior Vice President who is not disqualified on that ground shall make the appointment.
    3
  • Except as otherwise agreed, the arbitration tribunal shall determine the limits of its jurisdiction in accordance with this Agreement and shall establish its own procedure. At the direction of the tribunal or at the request of either of the Contracting Parties, a conference to determine the precise issues to be arbitrated and the specific procedures to be followed shall be held no later than fifteen (15) days after the tribunal is fully constituted.
    4
  • Except as otherwise agreed by the Contracting Parties or prescribed by the tribunal, each Contracting Party shall submit a memorandum within forty-five (45) days of the time the tribunal is fully constituted. Replies shall be due sixty (60) days later. The tribunal shall hold a hearing, at the request of either Contracting Party or at its discretion, within fifteen (15) days after replies are due.
    5
  • The tribunal shall attempt to render a written decision within thirty (30) days after completion of the hearing or, if no hearing is held, after the date both replies are submitted. The decision of the majority of the tribunal shall prevail.
    6
  • The Contracting Parties may submit requests for clarification of the decision within fifteen (15) days after it is rendered and any clarification given shall be issued within fifteen (15) days of such request.
    7
  • The decision of the tribunal shall be binding on the Contracting Parties.
    8
  • The expenses of the tribunal shall be shared equally between the Contracting Parties.
    9
  • If and so long as either Contracting Party fails to comply with any decision given under paragraph 3 of this Article, the other Contracting Party may withhold, revoke, suspend or limit any rights or privileges which it has granted by virtue of this agreement to the Contracting Party in default or to the Designated Airline or Airlines in default.

EY Taxlaw NL verschaft de mogelijkheid tot:
  • het full text doorzoeken van de verdragen en regelgeving met daarbij filters om het zoekgebied nader af te bakenen;
  • het full text doorzoeken van de gedelegeerde regelgeving, beleidsbesluiten en jurisprudentie;
  • het kunnen sorteren van de gedelegeerde regelgeving, beleidsbesluiten en jurisprudentie op datum, titel en instantie;
Responsive image
Responsive image
  • het oproepen van artikelversies tot enige jaren terug;
  • het maken van aantekeningen op artikelniveau;
  • de creatie van dossiers voor de opslag van snelkoppelingen naar veelvuldig geraadpleegde wetsartikelen;
  • het delen via mail en sociale media van artikelteksten met desgewenst een additioneel bericht.